In the previous news, we talked about the shipment of the third package (the previous two packages have worked for 6 years and are still working).
The client ordered the installation of packing for faster launch.
Automation of the laying of bags was not provided, since in this region it is easier for the client to use manual labor.
More
Our engineer arrived in Vladikavkaz and carried out the following work (took 5 days)
- The choice of the optimal place.
- He designed and made the drawings of inserts into silos, pneumatics, the location of the package and what height to put it.
- Ordered materials for installation.
- I thought in advance how the bag will be issued and transmitted further.
- After installation, I configured the package for accurate production and maximum speed.
Bottom line – packing is already working and pushing cement in production mode.